Surprise! NASA Artemis Lunar Program Schedule Likely to Slip Again, 2024 Landing Unlikely
An astronaut descends the ladder to explore the lunar surface. (Credit: NASA)

by Douglas Messier
Managing Editor

The latest in a series of updates from NASA’s Office of Inspector General (OIG) says that despite making significant progress on the $86 billion Artemis program, the space agency’s schedule for returning astronauts to the moon in four years is likely to slip. [Full report]

“Nonetheless, the Agency faces significant challenges that we believe will make its current plan to launch Artemis I in 2021 and ultimately land astronauts on the Moon by the end of 2024 highly unlikely,” the update said.

(more…)
  • Parabolic Arc
  • April 20, 2021
Maxar and Busek Thruster System for NASA Lunar Gateway Passes Critical Milestone
Concept art of Maxar’s Power and Propulsion Element with six Hall effect thrusters. (Credit: Maxar Technologies)

NATICK, Mass., March 18, 2021 (Busek Co. PR) — Busek Co., a developer of high-performance electric propulsion technology for space applications, and Maxar Technologies (NYSE: MAXR) (TSX: MAXR), a trusted partner and innovator in Earth intelligence and Space Infrastructure, confirmed today the successful completion of an end-to-end hot fire test campaign validating all major elements of the 6-kilowatt solar electric propulsion (SEP) subsystem for the Power and Propulsion Element (PPE) of NASA’s Gateway in lunar orbit.

(more…)
  • Parabolic Arc
  • March 19, 2021
NASA Awards Contract to SpaceX to Launch Initial Elements for Lunar Outpost
An illustration of the Gateway’s Power and Propulsion Element and Habitation and Logistics Outpost in orbit around the Moon. (Credits: NASA)

KENNEDY SPACE CENTER, Fla. (NASA PR) — NASA has selected Space Exploration Technologies (SpaceX) of Hawthorne, California, to provide launch services for the agency’s Power and Propulsion Element (PPE) and Habitation and Logistics Outpost (HALO), the foundational elements of the Gateway. As the first long-term orbiting outpost around the Moon, the Gateway is critical to supporting sustainable astronauts missions under the agency’s Artemis program.

(more…)
  • Parabolic Arc
  • February 9, 2021
NASA Perseveres Through Pandemic to Complete Successful 2020

WASHINGTON (NASA PR) — In 2020, NASA made significant progress on America’s Moon to Mars exploration strategy, met mission objectives for the Artemis program, achieved significant scientific advancements to benefit humanity, and returned human spaceflight capabilities to the United States, all while agency teams acted quickly to assist the national COVID-19 response.

(more…)
  • Parabolic Arc
  • December 28, 2020
Thales Alenia Space Chosen by Northrop Grumman to Provide Pressurized Module for HALO
Artist illustration of Northrop Grumman’s HALO module and the Power Propulsion Element which form the first critical component of NASA’s Gateway. (Credit: Northrop Grumman)
  • HALO (Habitation And Logistics Outpost): the initial crew cabin for astronauts visiting the lunar Gateway
  • Derived from Cygnus 10-year success story with Thales Alenia Space flight proven technologies
  • With HALO, Thales Alenia Space is strengthening its contribution to the Lunar Gateway

TURIN, Italy, December 7, 2020 (Thales Alenia Space PR) –  Thales Alenia Space, the joint company between Thales (67%) and Leonardo (33%), has signed a contract with Northrop Grumman to develop the pressurized module for HALO (Habitation And Logistics Outpost) that will be one of the first two elements to form the lunar Gateway which will be launched in late 2023.

(more…)
  • Parabolic Arc
  • December 7, 2020
Lunar Gateway Instruments to Improve Weather Forecasting for Artemis Astronauts
Artist’s concept of the Gateway Power and Propulsion Element, or PPE, and Habitation and Logistics Outpost, or HALO, in orbit around the Moon. The gold box on the right side of the image depicts the HERMES payload. The ERSA payload is the silver box just below it. (Credits: NASA)

by Miles Hatfield
NASA’s Goddard Space Flight Center

GREENBELT, Md. — One of the first things people want to know before taking a trip is what the weather will be like wherever they are headed. For Artemis astronauts traveling on missions to the Moon, two space weather instrument suites, NASA’s HERMES and ESA’s ERSA, will provide an early forecast. Weather in this case means energized, subatomic particles and electromagnetic fields hurtling through the solar system.

(more…)
  • Parabolic Arc
  • November 25, 2020
Northrop Grumman Completes Preliminary Design Review for NASA’s Gateway Crew Module
Artist illustration of Northrop Grumman’s HALO module and the Power Propulsion Element which form the first critical component of NASA’s Gateway. (Credit: Northrop Grumman)

Company based the design for HALO on its flight-proven Cygnus spacecraft

DULLES, Va., Nov. 18, 2020 (Northrop Grumman PR) – Northrop Grumman Corporation (NYSE: NOC) has successfully completed its initial preliminary design review (PDR) event for the Habitation and Logistics Outpost (HALO). The module will serve as living quarters for astronauts at the Gateway during lunar exploration missions.

(more…)
  • Parabolic Arc
  • November 18, 2020
OIG Audit: NASA Gateway Elements Behind Schedule, Over Budget
Artemis Gateway (Credit: Thales Alenia Space/Briot)

by Douglas Messier
Managing Editor

NASA’s attempt to use innovative acquisition practices to speed up development of the lunar Gateway has left the first two elements of the station over budget and behind schedule, according to a new audit from the space agency’s Office of Inspector General.

It is also unlikely the human-tended Gateway will be capable of supporting the planned 2024 mission to land American astronauts at the south pole of the moon, the audit concluded.

(more…)
  • Parabolic Arc
  • November 16, 2020
GAO: NASA Performance on Major Projects Continues to Deteriorate

The Government Accountability Office (GAO) released its latest assessment of NASA’s major projects at the end of April. It found that NASA’s performance on its major projects continued to deteriorate on cost and schedule. (Full Report)

Below are key excerpts from the report that provide an overview of where NASA stands on its major projects. Although GAO did not analyze the Artemis program to return astronauts to the moon, the watchdog warned the Trump Administration’s decision to move the landing date up from 2028 to 2024 will put more pressure on the space agency.

“Looking ahead, NASA will continue to face significant cost and schedule risks as it undertakes complex efforts to return to the moon under an aggressive time frame,” the report stated.

(more…)