NASA Inspector General’s Report Criticizes Agency’s Cost and Schedule Practices

NASA’s Space Launch System (SLS) rocket with the Orion spacecraft aboard is seen at sunrise atop a mobile launcher at Launch Complex 39B, Monday, April 4, 2022, as the Artemis I launch team conducts the wet dress rehearsal test at NASA’s Kennedy Space Center in Florida. (Credit: NASA/Joel Kowsky)

Congress is unable to make informed funding decisions about NASA’s multi-mission programs because the space agency is not providing it with federally mandated cost and schedule information, according to a new report from the NASA Office of Inspector General.

“Specifically, for the programs supporting Artemis, the Agency’s return-to-the-Moon and ultimately to Mars effort, NASA is circumventing required cost and schedule controls by categorizing certain production costs as operations costs when, in our opinion, they should be categorized as development costs,” the report said.