Artemis Update From the Department of Well Duh

NASA’s Office of Inspector General terminates audit of Artemis program with words of obviousness
by Douglas Messier
Managing Editor
NASA’s Office of Inspector General (IG) has determined that the biggest problem the space agency faces in its Artemis lunar program is….wait for it….money.
“Based upon our audit work completed to date, we found that the most significant challenge NASA currently faces in returning humans to the Moon by 2024 is budget uncertainty, a challenge that could ultimately affect the Agency’s ability to safely accomplish the mission,” the IG said in a memorandum published on its website.
Well, yeah….
These words of obviousness were contained in a Dec. 1 memo from Assistant Inspector General Audits Kimberly F. Benoit to Kathy Lueders, NASA’s associate administrator for human exploration and operations.
Benoit informed Lueders that OIG was taking the unusual step terminating a review of the Artemis program without issuing a report. The audit, titled NASA’s Challenges to Safely Return Humans to the Moon by 2024, was announced in August.
“The Office of Inspector General is closing its review of NASA’s challenges associated with safely returning humans to the Moon by 2024 because our initial work revealed the Agency, at this relatively early point in its efforts, appears to be taking proactive measures to address the major potential safety issues and risks,” Benoit wrote. “The objective of this audit was to identify top safety challenges and NASA’s actions to mitigate them.”
Well, it’s good to hear that NASA seems to be on top of the safety issue.
Since that memo was sent, Congress rendered the review unnecessary by driving a stake through the heart of outgoing President Donald Trump’s dream of returning astronauts to the moon in 2024.
In a budget approved last week, Congress provided only $850 million for the Human Landing System (HLS) that would take astronauts to and from the surface. The funding was well short of the $3.2 billion NASA said is needed to keep the agency on course for the 2024 landing.
By the time Benoit wrote her memo, the writing was already on the wall. The House of Representatives had weighed in by providing only $628 million in its funding bill. Trump, who had championed the 2024 landing date, had lost the election to Democrat Joe Biden.
The Senate subsequently provided $1 billion for HLS, which was still far short of what was needed for a 2024 landing. The House and Senate eventually comprised at $850 million.
What President-elect Joe Biden will do with the Artemis program is unknown. It is possible he will elect to continue the program with a later landing date, which will require a brand new plan.
Benoit said the IG would be there to evaluate whatever NASA comes up with for Artemis.
“In 2019 and 2020, we identified returning to the Moon as a top management and performance challenge and will continue our oversight of NASA’s management of the Artemis program and the Agency’s human exploration efforts through other audits and reviews. While we are closing this review, we may initiate a similar assessment in the future if conditions warrant,” she wrote.
The text of Benoit’s letter is below. I deleted contact information for a NASA official so he doesn’t get spammed.
NASA Office of Inspector General
December 1, 2020
TO: Kathy Lueders
Associate Administrator for Human Exploration and Operations Mission Directorate
Terrence W. Wilcutt
Chief of Safety and Mission Assurance
SUBJECT: Termination of Audit, NASA’s Challenges to Safely Return Humans to the Moon by 2024 (IG-21-007; A-20-014-00)
The Office of Inspector General is closing its review of NASA’s challenges associated with safely returning humans to the Moon by 2024 because our initial work revealed the Agency, at this relatively early point in its efforts, appears to be taking proactive measures to address the major potential safety issues and risks. The objective of this audit was to identify top safety challenges and NASA’s actions to mitigate them.
We announced this review in August 2020 in part because the NASA Aerospace Safety Advisory Panel raised concerns over the Agency’s plans to accelerate its return-to-the-Moon schedule and advised that “NASA must guard against undue schedule pressure that might lead to decisions adversely impacting safety and mission assurance.”1 The 2024 timeline was established to create a sense of urgency regarding returning American astronauts to the Moon, and NASA senior officials acknowledged the aggressiveness of this schedule. To meet our objective, we interviewed NASA officials and reviewed documentation related to NASA’s lunar missions, known as the Artemis program. We also observed congressional hearings with the NASA Administrator and attended public briefings of the Aerospace Safety Advisory Panel. We did not, however, complete an assessment of the effectiveness of internal controls during our review.
Based upon our audit work completed to date, we found that the most significant challenge NASA currently faces in returning humans to the Moon by 2024 is budget uncertainty, a challenge that could ultimately affect the Agency’s ability to safely accomplish the mission. NASA remains under a continuing budget resolution until December 11, 2020, with a second continuing resolution possible through the spring of 2021. The House of Representatives passed a bill to provide NASA $600 million in its fiscal year 2021 appropriations for the Human Landing System (HLS), a key component of its lunar program, but the Administrator stated that the Agency needs the full $3.2 billion in the President’s 2021 budget request no later than March 2021 to develop the HLS in time to meet the 2024 deadline.2
Despite this budget uncertainty, the Agency is taking steps to address a variety of potential safety issues. In one example, the Agency preserved a series of eight tests on the core stage flight hardware for the Space Launch System (known as the Green Run), rather than skipping these in favor of accelerating the testing schedule. Additionally, NASA officials told us they are applying lessons learned from the Commercial Crew Program to the HLS contracts, notably in the area of contractor insight and oversight, to ensure the Agency has all the information it needs as development progresses. Lastly, NASA has intentionally delayed the start of detailed safety analyses for the Artemis III mission (the proposed lunar landing) since designs for the HLS have not yet been finalized.3 The Artemis Plan released in September 2020 states that a preliminary design-level review will be conducted in early 2021.4 This would include identifying hazardous conditions, their causes, and the development of hazard elimination or mitigation strategies to determine which designs are the most mature and most likely to meet the 2024 timeline to return humans to the Moon. Based upon our audit work performed to date and the Artemis program schedule, we determined that further review at this time by our office would not be the best use of our or NASA’s resources.
While NASA has made significant progress to further its human exploration efforts, many questions remain about the total cost, schedule, and scope of the Agency’s lunar ambitions. Achieving a human lunar landing by 2024 will require strong, consistent, and sustained leadership from the President, Congress, and NASA, as well as stable and timely funding. In 2019 and 2020, we identified returning to the Moon as a top management and performance challenge and will continue our oversight of NASA’s management of the Artemis program and the Agency’s human exploration efforts through other audits and reviews.5 While we are closing this review, we may initiate a similar assessment in the future if conditions warrant.
We appreciate the courtesies and cooperation provided during this review. If you have questions about this memorandum, contact Laurence Hawkins, Audit Operations and Quality Assurance Director, at [DELETED].
Kimberly F. Benoit
Assistant Inspector General for Audits
Footnotes
1 Aerospace Safety Advisory Panel, Annual Report for 2019 (January 2020).
2 Commerce, Justice, Science, and Related Agencies Appropriations Bill, 2021, H. Rep. No. 116-455 (2020). As of November 2020, the Senate had yet to decide on NASA’s fiscal year 2021 appropriation.
3 In April 2020, NASA provided three companies—Blue Origin, Dynetics Incorporated, and Space Exploration Technologies Corporation—firm-fixed price, milestone-based contracts with a combined value of $967 million for a 10-month base period to design and develop the Agency’s HLS. During the base period, NASA intends to evaluate the companies’ designs and then select two of the three companies to continue HLS development for future Moon missions.
4 NASA, Artemis Plan: NASA’s Lunar Exploration Program Overview (September 2020).
5 NASA Office of Inspector General Top Management and Performance Challenges reports can be found at
https://oig.nasa.gov/challenges.html (accessed November 3, 2020).