OIG Audit: NASA Gateway Elements Behind Schedule, Over Budget

by Douglas Messier
Managing Editor
NASA’s attempt to use innovative acquisition practices to speed up development of the lunar Gateway has left the first two elements of the station over budget and behind schedule, according to a new audit from the space agency’s Office of Inspector General.
It is also unlikely the human-tended Gateway will be capable of supporting the planned 2024 mission to land American astronauts at the south pole of the moon, the audit concluded.
In March 2019, Vice President Mike Pence announced the administration was moving the landing date up by four years from 2028 to 2024. NASA accelerated acquisition for the Gateway, a small station designed to support exploration of the moon and its surface.
NASA competitively awarded a $375 million contract to Maxar Technologies to develop the Gateway’s Power and Propulsion Element (PPE) in May 2019.
Two months later, the space agency awarded a $187 million contract that was not competed to Northrop Grumman to build the Habitation and Logistics Outpost (HALO), which provides living and working space for astronauts and a docking port for the Orion spacecraft.
The HALO contract didn’t cover the full price for developing the module. Instead it allowed Northrop Grumman to design the habitat up through the preliminary design review. The contract has been increased to $240.4 million.
The audit found that the NASA awarded the contracts before the requirements for the two elements and the Gateway were finalized. The space agency hadn’t decided whether the station will be necessary to support the planned moon landing in 2024.
“In our judgment, NASA’s acceleration of the acquisition for both the PPE and HALO before fully defining the Gateway’s requirements added significant costs to the projects’ development efforts and increases the risk of future schedule delays and additional cost increases,” the audit said.

Maxar’s contract for the PPE has increased by $78.5 million to $453.5 million since NASA awarded the contract. The audit said additional increases are expected to accommodate evolving requirements and technical challenges.
NASA’s decision to launch both the PPE and HALO on one commercial launch vehicle instead of on separate rockets has been one of the drivers of the requirements changes. Several components had to be redesigned to accommodate the combined launch.
Although the decision saved NASA the cost of a second launch, it required Maxar to terminate its launch contract for the PPE with SpaceX after already paying $27.5 million to Elon Musk’s company.
“Further, a co-manifested launch increases risk because together the elements may be too heavy for commercially available rockets or too long for the rocket’s fairing, potentially impacting intended spacecraft mass, length, and other requirements,” the audit said.
“If it is able to address these risks, NASA may receive benefits from co-manifesting, such as avoiding a rendezvous in orbit by integrating both components on the ground before launch,” the document added.
The changes have resulted in launch delays.
“The PPE is likely to launch at least 17 months behind its original date of December 2022 while HALO has 2 to 5 months of schedule risk, potentially moving its launch readiness date further into 2024,” the audit said. “Compounding these issues is the 2024 lunar mandate that drove the accelerated development schedule in the first place and resulted in a lack of schedule margin in the Gateway Program.”
The delays make it unlikely the Gateway will be ready to support a landing in 2024. Adding to the uncertainty is the fact that NASA has awarded a contract to build the Human Landing System that will take astronauts to the lunar surface. The space agency has awarded design contracts to Blue Origin, Dynetics and SpaceX.
A 2024 landing date seems increasing unlikely in any event. House and Senate spending bills for fiscal year 2021 do not provide the $3.4 billion NASA has said it needs this year to keep the program on schedule. The Senate bill provides $1 billion, the House bill only $628.2 million.
The accelerated lunar program is also an initiative of the outgoing Trump Administration. It is not clear if Biden Administration will maintain the 2024 target.
The audit’s results in brief section is reproduced below.
NASA’S Management of the Gateway Program for Artemis Missions
NASA Office of Inspector General
Report No. IG-21-004
November 10, 2020
RESULTS IN BRIEF
Why We Performed this Audit
In March 2019, the Administration directed NASA to execute a plan to land humans on the Moon’s South Pole by 2024, 4 years sooner than NASA’s intended schedule. In response, the NASA Administrator announced that the return-to-the Moon mission would be known as Artemis and the Agency would use innovative acquisition practices to help accelerate the timetable. The Artemis program includes two exploration missions to orbit the Moon in 2021 and 2023 using the Space Launch System rocket and Orion Multi-Purpose Crew Vehicle (Orion), both of which remain under development and have yet to be flown together. To conduct a lunar landing, the Agency must develop a Human Landing System, complete development of a new spacesuit, and conduct robotic exploration of the proposed landing sites. Moving forward, NASA also plans to build the Gateway—essentially, a small space station—to provide a staging location for additional lunar missions and future deep space operations.
Gateway’s initial elements, scheduled to launch together in early 2024, consist of the Power and Propulsion Element (PPE), which powers and propels the spacecraft in orbit, and the Habitation and Logistics Outpost (HALO), which provides a docking location for the Orion capsule and living and working spaces for crewmembers. To date, NASA has spent over half a billion dollars and almost 3 years of design work on the PPE and HALO. To reduce the time needed to acquire these two Gateway elements, NASA modified its standard acquisition practices and instead used a fixed-price contract designed for commercial research and development and a sole-source award. Specifically, the Agency competitively awarded a contract to Maxar Technologies (Maxar) in May 2019 to develop the PPE and made a sole source award to Northrop Grumman (Northrop) in July 2019 for the HALO. The Agency awarded these contracts before requirements were firm and before it decided whether to use the Gateway to support the planned 2024 Moon landing.
This report is one in a series of audits examining NASA’s Artemis program. In this audit, we assessed to what extent the PPE and HALO are meeting schedule, cost, and performance goals. To complete this work, we reviewed the Gateway’s schedule, funding documentation, and acquisition method. For PPE and HALO, we reviewed contract files, cost and budget documentation, performance updates, schedule data, and technical risks. We also reviewed HALO’s sole-source documentation. In addition, we interviewed NASA, Maxar, and Northrop officials.
What We Found
The development schedules for both the PPE and HALO have been negatively impacted by the Agency’s still-evolving Gateway requirements, including NASA’s decision to co-manifest and launch the two elements on the same commercial rocket rather than separately as initially intended. Given this decision, the PPE is likely to launch at least 17 months behind its original date of December 2022 while HALO has 2 to 5 months of schedule risk, potentially moving its launch readiness date further into 2024. Compounding these issues is the 2024 lunar mandate that drove the accelerated development schedule in the first place and resulted in a lack of schedule margin in the Gateway Program. While NASA policies identify the need for sufficient schedule margin in development programs, we found Gateway officials had no guidance on suggested margins from the Human Exploration and Operations Mission Directorate (HEOMD) —organizationally where the Gateway Program is located—to factor into their schedules. With both the PPE and HALO elements highly dependent on each other due to the decision to co-manifest the systems, coupled with an expected 10-month travel time to lunar orbit, the Gateway likely will not be in a position to support a 2024 lunar landing.
The decision to launch the PPE and HALO together, while avoiding the cost of a second commercial launch vehicle, has contributed to cost increases due to the redesign of several components, an elevated launch risk, and a longer duration flight to lunar orbit. In addition, due to the decision Maxar was forced to terminate its subcontract with Space Exploration Technologies Corp (SpaceX) for PPE launch services, even though Maxar had already paid SpaceX approximately $27.5 million for this service, a portion of which was paid by NASA prior to the termination. Further, a co-manifested launch increases risk because together the elements may be too heavy for commercially available rockets or too long for the rocket’s fairing, potentially impacting intended spacecraft mass, length, and other requirements. If it is able to address these risks, NASA may receive benefits from co-manifesting, such as avoiding a rendezvous in orbit by integrating both components on the ground before launch.
NASA selected Maxar in May 2019 to provide the PPE under a fixed-price contract because the Agency anticipated few design and development changes. However, the contract value has increased by $78.5 million since the award, with more increases expected to accommodate additional evolving requirements and technical challenges. PPE has also experienced other contract management challenges, including the collapse of negotiations between Maxar and a subcontractor to provide its high-power electric propulsion system.
For HALO, the Agency awarded Northrop a sole-source contract in order to meet the 2024 goal. Despite NASA’s standard requirement to definitize a contract’s final terms, conditions, and costs within 6 months of issuance, the Agency did not definitize the contract with Northrop for 10 months due to the lack of defined requirements. Moreover, NASA and Northrop had only agreed to contract costs on a cost-reimbursable basis for a 7-month design phase. The Agency plans to spend over $200 million on habitation design by January 2021, and we anticipate a significant increase in cost if NASA is unable to negotiate the 2021 to 2026 performance period as fixed-price. We also expect further schedule delays and cost increases for HALO due to additional undefined requirements, adjustments to projected budgets that removed a second U.S. habitat, and technical challenges.
In our judgment, NASA’s acceleration of the acquisition for both the PPE and HALO before fully defining the Gateway’s requirements added significant costs to the projects’ development efforts and increases the risk of future schedule delays and additional cost increases.
What We Recommended
To increase the efficiency and effectiveness of NASA’s Gateway Program, we recommended NASA’s Associate Administrator for HEOMD:
(1) baseline the Gateway requirements and specifications in contract modifications prior to updating and awarding the PPE and HALO fixed-price contracts;
(2) ensure PPE and HALO delivery and launch dates are realistic by including sufficient schedule margin in their development schedules;
(3) develop a HEOMD policy that establishes a reasonable amount of recommended schedule margin by phase of program or project;
(4) confirm at selection the launch system provider for the co-manifested PPE and HALO will meet spacecraft mass, length, and other requirements
(5) work with the contractors to obtain a credit for the amount already spent on launch services under the PPE contract;
(6) take action to enforce NASA policy to definitize contracts within 6 months of award;
(7) definitize the remaining development and delivery portion of the HALO contract by Preliminary Design Review plus 3 months; and
(8) ensure the maturity of system requirements are fully understood before selecting the acquisition method and contract type for future acquisition strategies supporting Artemis and Mars missions.
We provided a draft of this report to NASA management who concurred with our recommendations and described planned actions to address them. We consider the proposed actions responsive to our recommendations and will close the recommendations upon their completion and verification.
6 responses to “OIG Audit: NASA Gateway Elements Behind Schedule, Over Budget”
Leave a Reply
You must be logged in to post a comment.
There’s pretty simple answer to this mess – let the contractors drive the requirements from here on out.
Simple, but wrong. That’s how we got Constellation and SLS.
Simpler than that. Lock in the design before start. Hard fixed price bid. Paid when complete with intermediate draws based on percent complete. Changes during construction penalize the contracting agency. Get your moronic incompetent oversight people out of the way.
Running behind and need operating cash?
Costing more and you are going to lose money?
Draw denied because you failed to meet spec?
Get your TS slips at the chaplains office.
Works reasonably well in construction. Not perfect of course. Many engineers and architects need their credentials revoked. Plus the 30 year rookie problems in the field.
NASA should stop trying to save money as saving money seems to just make projects more expensive in the NASA way of doing ventures.
About the fairing needed to launch a combined PPE/HALO, NASA was simply anticipating that SpaceX would be developing and then providing a larger fairing due to the requirements of the big Air Force contract they were strongly pursuing. And of course SpaceX won a share of the Air Force contract and will in fact be developing the needed larger fairing.
Beyond that, yeah, awarding a contract to develop and build something to exacting requirements before you’ve defined what exactly it is that you want to be developed and built, or even what exactly it is for is…bound to waste money.
Another Doug Loverro Special (Bridenstine’s done a great job overall, but that whole Loverro chapter has got to have been Bridenstine’s biggest swing and miss)
So…I wonder if combining the launches was Loverro’s attempt to give Boeing and SLS an advantage over the competition, like he apparently tried to give Boeing an advantage over the HLS competition.